Napa electrical project

KEYANO COLLEGE

 
FLOOD RESTORATION – MAIN LAB FACILITY

This multi-million dollar restoration saw a peak manpower commitment of fifty six Division 26 employees between May 15, 2020 and August 15, 2020. The General Contractor for the project was Belfor Property Restoration.

Rebuilding an advanced training facility entailed many complicated circumstances. We are proud to have a management team with enough experience to function on levels that would normally be managed by an engineering group. This is supported by over 40 years of combined experience in management, quality assurance, and construction execution on complex industrial projects.

Division 26 was pleased to have played a key role in the successful completion of the work for this important and respected institution. We believe that our success is largely the result of having a team with the ability to think in advance, communicate, collaborate, and apply their experience collectively.

“This was a technically complex, multi-faceted project and the fact that it was successfully completed without a formal engineering group is a testament to the talent and expertise that Division 26 brought to the job. A team of rock stars in my books!”
– Director of operations, Belfor Canada

Project activities included:

  • Technical Assessment
  • Planning
  • Coordination and Scheduling
  • Procurement
  • Execution
  • Commissioning
  • Turn Over
  • Additional Scope and Upgrades
  • Completion
Napa electrical project

Syncrude Sport & Wellness Centre

 
  • Removal and replacement of over 250 receptacles and devices.
  • Installation of new boxes, connectors, AC-90, and conduit
  • Removal of all low voltage wiring and data runs (over 300 ) from 45 plus in-slab conduits
  • Removal of water and swabbing of conduits, and replacement of new cables in above conduits
  • Removal and replacement of new 300 KVA transformer and 400 amp disconnect
Napa electrical project

CUMMINS

 

Project activities included:

Demolition, replacement, and installation of damaged:

  • Panel boards and transformers
  • 600 volt service feeder conductors
  • Customer mechanical repair equipment
  • Parking lot distribution equipment
  • Parking lot receptacles
  • Fire alarm devices
  • Communication systems
  • Elevator equipment

Demolition, replacement, and installation of:

  • New office branch circuitry and outlets
  • Emergency lighting systems

Testing and commissioning of:

  • All electrical systems and backup generator
  • Fire alarm system
  • All communications systems
Napa electrical project

NAPA

 

Project activities included:

Demolition, replacement, and installation of damaged:

  • Panel boards and transformers
  • New office branch circuitry and outlets
  • New emergency lighting systems
  • Fire alarm devices
  • Communication systems
  • Conduits and cabling
  • HVAC equipment and control systems

Installation, wiring and testing of:

  • Backup generator system

Testing and commissioning of:

  • All electrical systems
  • Fire alarm system
  • All communications systems
Napa electrical project

8520 MANNING AVE

 

Project activities included:

Installation of:

  • Temporary 600 volt electrical system to service building

Demolition, replacement, and installation of damaged:

  • Main Switch gear, panel boards and transformers
  • 600 volt service feeder conductors
  • Conduits and cabling
  • Tenant feeder cables
  • Parkade lighting systems
  • Parkade fire alarm devices
  • Communication systems
  • Elevator equipment
  • Conduits and cabling
  • HVAC equipment and control systems

Demolition, replacement, and installation of:

  • New parkade branch circuitry and outlets
  • Parkade emergency lighting systems

Testing and commissioning of:

  • Fire alarm system
  • All communications systems

Relocation of:

  • Main electrical service to 2nd floor
Napa electrical project

PENHORWOOD HOUSING

 

Project activities included:

Demolition, replacement, and installation of damaged:

  • Communications systems
  • Cabling
  • HVAC equipment and control systems
  • Parking lot receptacles

Demolition, replacement, and installation of:

  • Branch circuitry and outlets

Testing and commissioning of:

  • All electrical systems

Re-energization of buildings

Napa electrical project

ACDEN

 

Project activities included:

Demolition, replacement, and installation of damaged:

  • Panel boards and transformers
  • 600 volt service feeder conductors
  • Customer mechanical repair equipment
  • Parking lot distribution equipment
  • Parking lot receptacles
  • Fire alarm devices
  • Communication systems
  • Elevator equipment

Demolition, replacement, and installation of:

  • New office branch circuitry and outlets
  • Emergency lighting systems

Testing and commissioning of:

  • All electrical systems and backup generator
  • Fire alarm system
  • All communications systems